Oklahoma County advisory panels receive ARPA project updates; elevators, behavioral health space near completion

December 08, 2025 | Oklahoma County, Oklahoma


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Oklahoma County advisory panels receive ARPA project updates; elevators, behavioral health space near completion
Oklahoma County advisory members on Monday received progress reports on ARPA-funded capital projects, with the owner’s representative saying elevator work and interior fit-outs are nearing completion and other tasks remain pending inspections and equipment deliveries.

Bill, the owner’s representative, told the infrastructure advisory meeting that abatement at the annex is complete and officials are "waiting for some, DOL inspections," adding, "Metro 2 has been inspected and we have the state requirement final state punch list that we're working through, and then we'll begin Metro 1." He described the ICB elevator as "about 98%" complete but said crews are waiting for permanent power from Lingo, and that the fifth floor is similarly "98% done," with low-voltage terminations and a furniture schedule still outstanding.

The report covered additional items: front-entrance ductwork inspections, entry-frame work, and ongoing progress on the behavioral health services space despite weather-related delays. Bill said several fixtures and furnishings — including lockers, appliances, signage and benches — have been ordered and are expected in late December, and that Lingo has committed to finish low-voltage work off-site in January.

Board members asked for timing and contractor details; the transcript records a planned kickoff meeting with the contracted management firm on the 16th. A member moved to "receive" the owner’s representative report, the motion was seconded and the advisory body voted to receive the report. The transcript does not list a roll-call vote tally or individual vote names.

The chair reported that the Citizens Bond Oversight Advisory Board had met and received vendor updates on the behavioral health center and the detention-phase work; members had "a few good questions" but no substantive new items were reported.

The infrastructure session adjourned, and the PBA advisory meeting convened later the same day to consider related ARPA project updates.

Next steps cited in the reports include pending DOL and final inspections, completion of remaining low-voltage terminations and furniture installation scheduling; the owner’s representative and project teams will continue coordinating with contractors and county staff.

Don't Miss a Word: See the Full Meeting!

Go beyond summaries. Unlock every video, transcript, and key insight with a Founder Membership.

Get instant access to full meeting videos
Search and clip any phrase from complete transcripts
Receive AI-powered summaries & custom alerts
Enjoy lifetime, unrestricted access to government data
Access Full Meeting

30-day money-back guarantee

Sponsors

Proudly supported by sponsors who keep Oklahoma articles free in 2025

Scribe from Workplace AI
Scribe from Workplace AI