Norwood committee approves $1.28M vendor invoices, a $127,854 change order and moving amendment

Norwood School Building Committee · December 9, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Norwood School Building Committee approved $1,284,768.94 in monthly invoices, a $127,854 WT Richards change order and a $34,268.30 moving amendment; staff reported $138.9M committed of a $150M project budget and ongoing MSBA reimbursements.

The Norwood School Building Committee on Dec. 8 approved the monthly vendor invoice package totaling $1,284,768.94, authorized a WT Richards change order (No. 27) totaling $127,854 and approved an amendment for additional moving services totaling $34,268.30.

Project staff presented the invoice package, which included Vertex’s OPM invoice ($113,572.35), an architectural invoice ($18,636.21), WT Richards construction requisition ($1,076,807.42), technology invoices ($45,835.38), FF&E invoices ($8,445.09) and approximately $21,472 in other project expenses such as temporary way‑finding signage and waste management. The committee moved and seconded the vendor invoice package; the voice vote passed despite a recorded 'no' from one member and a 'symbolic' no comment from another.

Staff also reviewed Change Order 27 line items totaling $127,854, including plumbing/electrical and equipment PCOs (examples: an active HDMI cable replacement $31,423; window film installs $64,446; a returned‑equipment credit $5,400) and multiple smaller items. The committee approved the change order by voice vote after a motion and second.

On FF&E and technology, staff reported an FF&E budget of $2,370,249 and a technology budget of $2,337,751 with about $393,007.62 remaining to commit. Staff requested approval for an additional moving services amendment to cover increased crate counts and shelving; the amendment totaling $34,268.30 was moved, seconded and approved by voice vote.

In a broader budget update, staff said $138,935,453 of the $150,000,000 project budget had been committed and the project was tracking roughly $11,000,000 under budget at the end of November. The Massachusetts School Building Authority (MSBA) reimbursement process was discussed: $81,000,000 in eligible costs had been submitted and the MSBA had reimbursed just over $44,000,000, with several items still pending review. Staff also reported open change orders estimated at about $1,300,000; if all proceed, about 15% of the owner’s revised contingency would be spent.