Indian Trail staff outline five-year road resurfacing progress and near-term plan

Indian Trail Town Council · November 10, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works reviewed progress on the town's five-year resurfacing plan, recent contracts and funding sources and proposed a $1.2 million near-term contract to finish subdivision work and upgrades tied to a Navajo Veil complete-streets project.

Indian Trail — Public Works updated council on the town's five-year resurfacing plan established in October 2022, reported progress from three recent resurfacing contracts and proposed a $1.2 million near-term contract to complete remaining streets.

Todd Hunsinger said the town's 2021 pavement-condition survey showed 63% of town streets scored below the goal; the 2022 plan targeted a town-wide average of 80. Hunsinger summarized recent contracts: a July 2022 contract of $2.5 million (3.4 miles, 20 streets), a March 2024 $3.0 million contract (8.99 miles, 33 streets) and an Aug. 2024 $3.2 million contract (8.53 miles, 33 streets), totaling roughly $9.9 million spent of a planned $15.06 million program. He reported current per-mile resurfacing estimates near $300,000.00 and explained that state grant funds had been exhausted; future work will rely on capital reserves and the Powell bill funding.

Staff recommended proceeding with a $1.2 million contract this budget year to finish multi-phase subdivisions (Brookhaven, Sutter Ridge/Brook Valley) and to upgrade Navajo Veil in preparation for a future roundabout and complete-streets project. Hunsinger said typical resurfacing life is 10–15 years and noted a policy emphasis on pavement-preservation techniques to extend service life.

What happens next: Staff will complete the current $1.2 million contract, await the results of the latest pavement-condition survey (expected in about a month) and return to council with options for additional contracts and proposed funding sources in the next budget cycle.