Council authorizes fiber installation to new DPW facility; lead time cited at 20–30 weeks

October 23, 2025 | West Allis, Milwaukee County, Wisconsin


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Council authorizes fiber installation to new DPW facility; lead time cited at 20–30 weeks
West Allis Common Council members approved a resolution authorizing Cable Comp to furnish and install fiber‑optic infrastructure to the new Department of Public Works facility. Council members were told the work is needed to support the DPW data center and IT systems.

A city staff member explained that the electrical/DPW crews had installed conduit in advance but the fiber itself must now be pulled to the new facility. “The lead time is, like, 20 to 30 weeks. So we need to do this right now,” the staff member (Derek) said. Staff also stated the budget for the work is out of the new DPW project budget.

A motion to approve the resolution was moved and seconded and passed on a voice vote. The resolution authorizes contracting to obtain the fiber installation; staff noted long delivery lead times as the reason to proceed immediately.

View full meeting

This article is based on a recent meeting—watch the full video and explore the complete transcript for deeper insights into the discussion.

View full meeting

Sponsors

Proudly supported by sponsors who keep Wisconsin articles free in 2025

Scribe from Workplace AI
Scribe from Workplace AI