Summer Street reconstruction: board approves time extensions for change orders

5523849 · August 1, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved time-only change orders 9–12 for the Summer Street reconstruction project, citing winter shutdown and utility relocation delays by AT&T and NIPSCO.

The board approved time extensions for change orders 9 through 12 on the Summer Street reconstruction project, noting no change in the project’s cost. A staff member explained that the primary reasons for the requested extensions were a winter shutdown and delays caused by utility relocations by AT&T and NIPSCO.

“These are simply time extensions. There's no economic, impact. Our project increased cost. The bulk of it was a winter shutdown,” the staff member said when presenting the request submitted by Dean Button. The staff member also said the other delays were “basically utility, relocation delays by AT and T and NIPSCO gas.”

A board member recommended approval and the board concurred. The action recorded at the meeting was administrative: extend the contract schedule for the four change orders. The change orders did not include additional money, and the board did not alter scope.