Committee approves invoices, applications for payment and two change-order reductions
Get AI-powered insights, summaries, and transcripts
SubscribeSummary
The Property Facilities Committee voted to approve CHA invoices and several contractor applications for payment and accepted two change orders that reduced flooring project costs; the approvals were made by voice vote at the Sept. 3 meeting.
At the Sept. 3 Property Facilities Committee meeting, members moved and approved payment items listed under “items requiring action,” including CHA invoices numbered 1 through 10 and contractor applications for payment numbered 1 through 8. Committee members also approved two change orders that reduced previously billed amounts for flooring work.
During the agenda discussion staff listed a set of applications for payment including Phase 3 stormwater payments to Rutledge, partial flooring payments for JM Hill and other schools, and a JTL data-network invoice. After discussion, a motion to pay the CHA invoices (1–10) was made and the committee approved the motion by voice vote. A subsequent motion to approve applications for payment (1–8) likewise passed by voice vote.
Change orders presented included: • Resco (Resica/Resaca) flooring change order 1: decrease of $22,760 • JTL flooring change order from Cope: decrease of $48,160
A motion to approve change orders 1 and 2 passed by voice vote. The meeting record shows the committee answered “Aye” during roll calls for those motions; no individual recorded roll-call votes were read aloud in the transcript.
Committee members asked questions about partial flooring schedules and whether projects could have been consolidated to reduce costs; staff explained the “partial” designation reflected earlier phases of work and decisions to convert remaining waxable VCT flooring to LVT as part of multi-year scheduling. Staff also explained the district can adjust final invoicing to reflect credits tied to design/contract adjustments and that CHA invoicing would be adjusted if project prices change.
All motions described in this item were approved during the Sept. 3 meeting; the committee then adjourned.