Gardner identifies funds and contractor route to finish Mackie Park repairs

5789380 · August 25, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff said they located roughly $37,717.68 in leftover project funds and plan to reclassify additional money to reach an estimated $50,000–$52,000 needed to finish ADA-compliant repairs at Mackie Park; the original contractor may perform the work via a contract amendment rather than a new bid.

City of Gardner staff told the Economic and Community Development Committee they have identified $37,717.68 in existing CDBG and park project funds and will reclassify additional balances to approach the estimated $50,000–$52,000 needed to complete repairs at Mackie Park.

Staff said funds moved so far include $14,772.53 transferred from a Perkins account and $18,253.44 from Park Street Park, producing the $37,717.68 total. Busy Bee, the original contractor for park work, told staff it can provide a reestimate; staff expect the contractor’s updated price by the end of next week or the following week.

Why it matters: Mackie Park’s remaining work was intended to make the park ADA-compliant; repairs have been delayed while staff located funding. Committee members acknowledged the delay but said the city has a plan to finish the job and avoid rebidding, which would add time.

Procurement approach: staff reported that, under the procurement laws cited in the meeting (Chapter 30B and the construction statute referenced in the record), the work can proceed as a contract amendment with the original contractor because the additional scope is “substantially similar” to the existing contract, and therefore a new two-week bid procurement is not required. Staff said the Inspector General’s office must approve in some cases because of elapsed time, so approvals are still needed.

Other project funding: staff also reported that Pulaski Park improvements (drainage at the dog park, new walking trail, rubber mulch) came in significantly under budget; those savings are the likely source of additional funds to finish Mackie Park.

Status and next steps: staff expect to confirm the final estimate from Busy Bee, confirm the remaining fund reclassifications at an upcoming meeting, and execute a contract amendment when funding and approvals are in place. Committee members asked staff to remember the procurement shortcut in future similar projects to save time.

Ending: staff said they will report progress in the September update; if schedule or funding changes occur they will notify the committee and public.