Brown County approves $48,291 net change order for building restoration; updated contract $852,008.05

5929604 · October 30, 2024

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved a change order for the county building restoration project that results in a $48,291 net increase and raises the updated contract total to $852,008.05; commissioners discussed remaining garage issues and future decisions.

The Brown County Board of Commissioners approved a change order for the county building restoration project that results in a net increase of $48,291 and brings the updated contract total to $852,008.05.

Judy Dash, building superintendent, and an assistant presented the change‑order information. The change order reflects an earlier $113,000 addition offset in part by returned or deleted equipment and a credit of about $65,000, leaving the net change of $48,291 that the commission approved. Commissioners noted there remain open questions about the long‑term plan for an attached garage; staff said the garage condition is stable for now but that further discussion and engineering recommendations will follow.

Motion and context

A motion to approve the change order was made by Weese and seconded by Denner; commissioners carried the motion by voice vote. The transcript records the updated contract total and a brief explanation of the credits and new work included in the change order.

Clarifying details

The transcript includes an itemized exchange indicating an initial $113,000 addition, a $66,000 deletion/credit, and the final change‑order amount of $48,291. The updated contract total recorded in the meeting was $852,008.05. Commissioners and staff said they will continue to review long‑term options for the garage and the engineering report from IMEG was discussed as the next step.

Provenance (transcript excerpts)

Topic intro excerpt: "We got a change order for the building restoration ...".

Topic finish excerpt: "We have motion by Weese, second by Denner to approve the change order in the, contracts ... All in favor signify by saying aye. Aye. Opposed nay? Motion carries."