In a recent meeting of the Capital Outlay Committee for Coffee County, Tennessee, significant progress was reported on ongoing construction projects, including a new building and an animal shelter. The discussions highlighted the swift advancements made by the construction teams, with interior and exterior work nearing completion.
The committee noted that color selections for the interior are 90% complete, while the exterior work has reached full completion. Key structural elements, such as the metal building's roof and framing, are also well underway, with the back wall framing approximately 80% complete. The construction team is reportedly working diligently, with long hours dedicated to ensuring timely progress.
However, the meeting also addressed an unexpected challenge encountered during the excavation for utility lines. A large, existing septic tank was discovered, necessitating additional work to remove it. The committee discussed a proposed change order of $2,940 to cover the costs associated with this unforeseen issue, which includes excavating the tank, hauling away its contents, and ensuring the site is properly prepared for further construction.
The committee emphasized the importance of addressing this issue promptly to avoid future complications, as the septic tank's presence could have led to structural problems in the parking area. The approval of the change order is crucial for the continuation of the waterline installation, which has already made significant progress.
Overall, the meeting underscored the ongoing commitment of Coffee County officials to manage construction projects effectively while navigating unexpected challenges. The committee is expected to vote on the proposed change order in the coming sessions, ensuring that the projects remain on track for completion.