The Allen County Commissioners made significant strides in infrastructure planning during their January 3, 2025 meeting, approving multiple contracts aimed at enhancing local roadways and bridges.
The commissioners unanimously approved a consulting contract with Clark Dietz Inc. for right-of-way services related to the Cubio Ridge project, allocating $18,200 for the necessary appraisals and negotiations. This project is set to be bid in July 2027, with 80% of the costs reimbursed through the Fort Wayne District of NDOT.
In a related move, the board also greenlit a $7,640 contract with the same firm for right-of-way services for the Woodburn Road bridge replacement. This project will expand the bridge to accommodate a new trail, reflecting the county's commitment to improving both transportation and recreational infrastructure.
Commissioner Hartman addressed concerns about the lengthy timeline for these projects, explaining that the extensive appraisal and negotiation processes can take up to six months, especially if condemnation is necessary. He emphasized the importance of adhering to timelines to secure federal funding and avoid project delays.
Additionally, the commissioners approved an amendment with Versus Engineering for $10,000 to conduct a subsurface geotechnical study for the Fisher Road bridge project. This study is crucial for determining the necessary depth of the bridge's pilings, ensuring structural integrity.
In a proactive response to flooding issues on Still Avenue, the board declared an emergency to expedite the replacement of outdated drainage systems. The plan involves replacing 4-inch pipes with 12-inch ones, significantly increasing capacity and addressing flooding concerns for local residents.
These decisions underscore the commissioners' focus on infrastructure improvements and public safety, with a clear commitment to utilizing federal funds effectively while addressing community needs.