The Abilene Board of Building Standards convened on July 2, 2025, to address ongoing compliance issues regarding a condemned property. The meeting focused on case 24-000345, involving the owner of a building who has failed to submit necessary documents for renovation permits despite multiple reminders.
Mr. Wright, a representative from the city, reported that the contractor, Onyx Solutions, has not provided the required estimates and documentation to move forward with the project. As a result, the owner is facing civil penalties for non-compliance, amounting to $27,200 for 272 days of delay. The board emphasized that the entire building remains condemned, and partial renovations are not permissible until full compliance is achieved.
During the public hearing, Jack Oduro from Mariah Brokerage Services spoke on behalf of the owner, stating that efforts have been made to secure the property and obtain estimates for renovations. He noted that the owner has invested approximately $15,000 in architectural drawings and is seeking additional funding for a comprehensive renovation project estimated to cost between $5 million and $6 million. However, Oduro acknowledged that delays from Onyx Solutions have hindered progress.
Board members expressed frustration over the lack of timely action from the owner, with some advocating for the enforcement of civil penalties due to the prolonged inaction. The meeting concluded with a consensus that the owner must expedite compliance efforts to avoid further penalties and ensure the safety and usability of the property.
The board's next steps will involve monitoring the situation closely and potentially reassessing penalties if compliance is not achieved in a timely manner.