In a recent workshop held by the Leander City Council on June 25, 2025, officials discussed critical infrastructure options aimed at addressing the growing transportation needs of the community. The meeting focused on three proposed options for roadway improvements, each with varying costs and timelines, reflecting the city's commitment to enhancing traffic capacity while accommodating ongoing county projects.
The first option presented involves a redesign that would incur an additional cost of $2.2 million and extend the project timeline by eight months. This option allows the county to proceed with its original project while the city works on increasing roadway capacity to meet current and future demands. The design includes the construction of frontage roads, preserving space for future expansions.
The second option, which would extend the roadway further towards Harmony School, is estimated to cost around $7 million and would take an additional 18 to 24 months to complete. This plan proposes two lanes in each direction, with a temporary pavement connection to facilitate ongoing construction.
The most ambitious of the three options, option three, proposes three lanes in each direction from US 183 to Reagan Boulevard. This option has seen a significant cost update, now estimated at approximately $28 million, which includes utility relocation expenses. The timeline for this option is projected at 24 months from the start of construction.
City officials emphasized the importance of these discussions, noting that the county's flexibility in presenting multiple options stems from the city's request for enhanced roadway capacity. The county aims to ensure that its project proceeds without unnecessary delays while accommodating the city's needs for improved traffic flow.
As the council deliberates on these options, they face the challenge of balancing immediate infrastructure needs with long-term planning. The decisions made in this workshop will have lasting implications for Leander's transportation landscape, potentially shaping the city's growth and development for years to come. The council is expected to continue discussions and seek clarity on funding responsibilities and construction timelines in future meetings.