The Jenks G.O. Bond Oversight Committee convened on May 12, 2025, to discuss several critical infrastructure projects aimed at enhancing the community's water systems and public safety. The meeting highlighted ongoing efforts to improve water distribution and address structural concerns regarding local bridges.
A significant topic of discussion was the planned expansion of the water line system. Currently, the water line servicing Commerce Park ends near South James and is set to be extended to 121st Street. This extension is crucial for supporting new developments on the west side of Highway 75, allowing for increased residential and commercial growth in the area. The committee noted that a developer is prepared to collaborate on this project, which underscores the importance of infrastructure in facilitating economic development.
Before you scroll further...
Get access to the words and decisions of your elected officials for free!
Subscribe for Free Another key issue addressed was the replacement of a water line associated with the pedestrian bridge, which suffered damage during a severe cold snap in February 2019. The committee has engaged engineers to design a comprehensive repair plan for the bridge, which has been deemed structurally compromised. The bridge's condition has necessitated the closure of certain areas to ensure public safety. The committee is moving forward with a loan from the Water Resources Board to fund these repairs, which are essential for the subsequent water line replacement.
Additionally, the committee discussed the Arkansas Riverbank stabilization project, which has been on hold pending decisions from the City of Tulsa regarding the proposed Low Water Dam. The preliminary design phase for the dam is now underway, but concerns were raised about the potential costs and funding challenges that may arise as the project progresses. While there is community interest in the dam and its potential benefits, the financial implications remain a significant consideration for local government entities.
In conclusion, the Jenks G.O. Bond Oversight Committee's meeting underscored the ongoing commitment to improving infrastructure and public safety in the community. As projects move forward, the committee will continue to navigate funding challenges and community needs, ensuring that Jenks remains a viable and attractive place for development. The next steps will involve finalizing contracts for engineering work and monitoring the progress of the Low Water Dam design.