The Houston Service Delivery Committee meeting on April 14, 2025, focused on the evaluation of project delivery methods for upcoming construction initiatives. The committee discussed the need for an efficient approach to expedite project timelines, particularly in light of aging infrastructure at local water treatment plants.
During the meeting, officials outlined four potential delivery options: traditional design-bid-build, design-build, progressive design-build, and construction manager at risk (CMAR). The traditional method was dismissed due to its lengthy process, while design-build options were deemed too risky for both owners and contractors, potentially leading to increased costs.
The committee ultimately recommended the CMAR approach, which involves two separate contracts—one with a designer and another with a construction manager. This method allows for a collaborative relationship between the designer and the construction manager while maintaining a direct contractual relationship with Houston Public Works. The CMAR model is expected to facilitate faster project delivery by enabling construction to commence during the design phase through early work packages. This approach also provides cost certainty with a guaranteed maximum price established early in the project, reducing the risk of unexpected expenses.
Additionally, the committee highlighted that local contractors preferred this delivery method, which could increase participation and ensure bids align with budget expectations. The meeting also addressed ongoing projects at water treatment plants, indicating that the new model would allow for better integration of these initiatives.
Looking ahead, the committee plans to initiate procurement in the summer of 2025, with the first phase of the project aimed at delivering 90 million gallons per day expected to reach substantial completion by February 2031. The remaining capacity is projected to be operational by February 1934. This timeline is critical as existing plants approach the end of their operational life, emphasizing the urgency of the proposed improvements.