As the winter chill settles over New Shoreham, the Town Council and School Committee gathered to discuss the progress of the ongoing school renovation project, which has exceeded expectations. Under the bright lights of the meeting room, officials shared updates that painted a picture of success amid the cold season.
The renovation, currently on hiatus until spring, has made significant strides. Originally slated to focus on the East and North sides of the school, the project team has impressively completed nearly the entire West Side ahead of schedule. This accomplishment places them about a month and a half ahead of their initial timeline, a fact that brought nods of approval from council members.
The remediation of the vermiculite issue, a concern that had previously loomed over the project, is now complete. While a small punch list remains—consisting of minor painting touch-ups and cleaning of ductwork—the bulk of the heavy lifting has been accomplished. The team is set to return in the spring to finalize the remaining tasks, with plans to wrap up the project by August.
As the meeting progressed, discussions also touched on upcoming work scheduled for February break, which will include drywall and ceiling repairs. These efforts are part of a broader commitment to ensure that the school environment is safe and conducive to learning.
With the renovation on track, the community can look forward to a revitalized school that promises to enhance educational experiences for students in New Shoreham. As the council members concluded their discussions, the sense of optimism was palpable, leaving residents eager for the next chapter in their town's development.