Kentucky Exposition Center outlines plans for Phase 2 expansion to boost capacity

February 18, 2025 | 2025 Legislature KY, Kentucky


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Kentucky Exposition Center outlines plans for Phase 2 expansion to boost capacity
The Kentucky House Standing Committee on Appropriations and Revenue met on February 18, 2025, to discuss the critical next steps for the Kentucky Exposition Center's expansion, particularly focusing on the transition from Phase 1 to Phase 2 of the project. The committee emphasized the urgency of moving forward with Phase 2, which is essential for accommodating the growing demand for space and services at the facility.

During the meeting, officials highlighted that Phase 1 is currently about 20% complete, with a projected opening date in December 2026. This phase includes a new 350,000 square foot building designed to significantly increase capacity for events, including livestock shows and sports tournaments. However, the pressing need for Phase 2 was underscored, as the facility is already out of space and struggling to meet client demands.

The committee was informed that Phase 2 will involve the demolition of the outdated West Wing, originally built in 1956, to make way for modern facilities that can better serve current and future clients. The anticipated economic impact of completing both phases is substantial, with projections estimating an annual economic contribution of approximately $683 million and generating around $32 million in state sales tax.

Officials stressed that the upgrades are not merely about expanding space but are crucial for maintaining competitiveness with other venues across the country. The need for modern infrastructure to attract and retain clients was a recurring theme, as existing facilities are unable to meet the evolving needs of event organizers.

The committee's discussions also touched on the logistical aspects of the project, including the timeline for starting Phase 2, which could begin within the next few months as enabling projects are initiated. The urgency to secure necessary utilities and equipment for Phase 2 was highlighted, given the long lead times for essential components.

In conclusion, the meeting reinforced the importance of legislative support for the continuation of the Kentucky Exposition Center's expansion, as officials aim to enhance the facility's capabilities and economic contributions to the region. The committee's backing will be crucial for ensuring that the project moves forward efficiently and effectively.

View full meeting

This article is based on a recent meeting—watch the full video and explore the complete transcript for deeper insights into the discussion.