Macomb County's Finance, Audit, and Budget Committee made significant strides in their recent meeting, focusing on a guaranteed maximum price (GMP) amendment for a major construction project. This amendment, which totals $136 million, encompasses 24 individual bid categories, including essential services such as electrical, plumbing, mechanical, fire alarm, landscaping, paving, and roofing.
The bids for this project were publicly opened on November 19, 2024, following an electronic advertisement by Granger Construction Company and Macomb County purchasing. The project team conducted post-bid interviews and provided award recommendations, showcasing a collaborative effort among various partners, including Granger Construction and architectural advisors.
Approval of this GMP amendment is crucial for the county to meet its obligations under the American Rescue Plan Act (ARPA) before the Department of Treasury's deadline of December 31, 2024. The committee expressed gratitude for the transparency and clarity of the disclosures presented, indicating a well-organized process.
While the GMP covers primary construction costs, it does not include professional services, environmental consulting, or full technology installations, such as monitors and wiring. These elements will be addressed in future discussions, ensuring that all aspects of the project are comprehensively managed.
As the committee moves forward, the anticipated approval at the full board meeting on December 12, 2024, will mark a significant step in advancing this vital infrastructure project for Macomb County, ultimately benefiting the community through improved facilities and services.